Installation of Rooftop Solar on Government Building in ABD area-Phase 1

Mangaluru Smart City has proposed a Installation of Solar Rooftop in Seventeen numbers of Government entity buildings premises. MSCL has appointed M/s Wadia Techno Engineering Services Ltd & Consortium as its project management company (PMC)

The Roof Top Solar PV Power System is being proposed on the roof top of different Government buildings in Mangaluru.

It is proposed to install grid-connected roof top solar PV projects on the roofs of entities as specified by MNRE vide notification no. 03/88/2015-16/GCRT dated 04th May’2016.

Total Project Cost : Rs. 7.08 Crores.

image

 

Agreement with Govt buildings signed only for 705 kW out of 1288 kW. ESI Hospital, MCC Building, Town Hall & MCC Building at Mallikatte has been commissioned. KFDC building panels have been erected. ZP Building, Pilikula & APMC work yet to start.